Swan Hill Emergency Department Project

6.05.22

The Emergency Department project has now moved into the Detailed Design phase of the project, which has seen the establishment of key user groups specific to Emergency, Community Health, Occupational Therapy and HARP, Pathology (Austin), Front of House, Security and Café. Key staff representation through all sessions to date has been solid and well represented.

The Detailed Design Phase has an allocation of four (4) workshops for each user group identified. Each workshop is followed up with an Executive group session providing a summary of each workshop and key areas for discussion and decision. Our final Detailed Design Workshop was held last week, following this final week of workshops the consultant team anticipates agreement and sign off of this phase of the project from Swan Hill District Health.

We will then commence with some early works so as to decommission the existing building (old Nurses home) in preparation for the construction phase. Our Early works package includes temporary fit out for Pathology, Café and Community Health staff and their relocation to off site locations for the duration of the project. The project team is currently working on the Construction phasing so as to ensure that while our build is in progress services on site are minimally interrupted.

10.6.21

The new $48.7 Million SHDH Emergency Department development project has officially commenced.

SHDH has held its first meeting for the new Emergency Department development with the Victorian Health Building Authority, the Department of Health and the appointed project consultancy team to officially commence this exciting $48.7 Million project.

The  new Emergency Department development  will include:

  • 15 treatment rooms plus a 4 bed Short Stay Unit
  • A small extension to Radiology
  • A new  entry into the Hospital  with a reception area
  • New  larger waiting areas
  • A new Café
  • Staff office and meeting areas

The project consultants appointed to support this development are:

  • Silver Thomas Hanley- Architects
  • Aurecon – Project Manager
  • Lehr Consultants International (Engineering Services)
  • Slattery (Quantity Surveyor)
  • Philip Chun Building Code Consultants (Relevant Building Surveyor)

The draft Project Program is summarised as follows:

  • Project feasibility & schematic design                                June 2021 to December 2021
  • Design development and contract documentation           January 2022 to July 2022
  • Early building works  to prepare site                                 January 2022 to June 2022
  • Major building works                                                        November 2022 to June 2024

Our Consultancy Team and the SHDH Project Team will be gaining both staff and community input into the project by way of specific User and Working groups through the design and development phase.

The flow chart below provides an overview of how this project will be managed.