07.08.2023
Community Rehab (CRC) Driveway NOW REOPENED
The Community Rehab Centre Driveway on McCrae St has been reopened after the project team completed rectification works on the existing driveway late last week. We sincerely thank you for your patience and support during the temporary closure.
25.07.2023
Community Rehab (CRC) Driveway Temporary Access restrictions.
To enable continued future use of the Community Rehab Driveway on McCrae St for as long as possible, the project team have planned rectification works to the existing driveway.
These works are scheduled to take place next week from Monday 31st July to Friday 4th August, inclusive.
The driveway will be closed for vehicle traffic during this period. Pedestrian access will be maintained with vehicle drop off and pick up at the Splatt St end of the driveway.
We thank you for your understanding and cooperation during this period.
25.05.2023
EXCITING ANNOUNCEMENT- ADDITIONAL FUNDING RECEIVED FOR THE ED REDEVLOPMENT PROJECT
On behalf of the SHDH Board of Directors, I am pleased to inform the community
that construction of the new Swan Hill District Health Emergency Department will
commence in the coming weeks following the announcement of additional funding
for the project in the State Budget.
We look forward to working with your support on this exciting development for our
community.
Yours Sincerely,
Andrew Gilchrist
Chair, Board of Directors
Swan Hill District Health.
10.3.2023
Smoking Ceremony Video
22.02.2023
Today, we had the honor of hosting a Traditional Smoking Ceremony to cleanse the old nurses home site to make way for the new Emergency Department build. The Ceremony included an incredible didgeridoo performance and cultural dance that had the crowd mesmerized. This event is an important part of the coming together of community and a step in the right direction to make the new building a more welcoming and comfortable space for all. A big thank you to all involved in making this event and process so special
Bring on the new build!!
23.01.2023
19.01.23
18.01.23
16.01.23
Demolition progress
12.01.23
Demolition of the old nurses home has begun today!
29.11.22
The contractor has commenced pre-demolition works on the old nurses home building, the excavator is onsite and has began the demolition of the old cafeteria and the external of the nurses home, the roof to the nurses home is due to be removed later this week.
Underground powerline works are on track to be completed by 14th December 2022
17.11.22
Works have started in McCrae Street with fencing barriers erected but we would like to confirm that our Community Rehabilitation Centre (CRC) located next door is still OPEN and continues to operate as normal.
We recommend you allow an extra 10-15 minutes prior to your appointment to find a car park as parking is currently reduced along McCrae Street. Where possible you are still able to utilise the drop off and and pick up bay directly in front of the CRC building.
We understand that these ongoing works can be an inconvenience, but you can be assured that we are still here and our wonderful team are ready to continue to provide the high standard of care that our community is used to
If you have any queries please do not hesitate to contact the team on 03 5033 9321.
10.10.22
Health Promotion, Breastfeeding Support, Women’s Health, Dietetics, Diabetes Education, Refugee Health, Sexual Health and Cancer Care services have relocated to 125 Campbell Street for a few years so the old nurses home can be demolished.
In line with the relocation Health Promotion affiliated services will have a name change to “Community Health”
12.09.22
7 new car parking spots available to the public!
From today, Monday 12th September, 7 carparks (including 1 disabled access) are available for public parking in the staff carpark at the back of the Hospital. A 1 hour time limit applies to these parks.
We hope that this provides easier access for the community to our services within the immediate area.
Stay tuned for further updates to be provided on the SHDH Facebook page and via media release.
15.08.22
As many of you would be aware, the Old Nurses Home (60 McCrae Street) is due to be demolished in October. To celebrate the history of the building and acknowledge the many and wonderful staff that resided there over 44 years. SHDH will be hosting the “Old Nurses Home Celebration Event– The End of an Era” on Wednesday 28th September and you’re invited!!
Afternoon tea will be provided along with a brief history of the nursing home, a ED Redevelopment Project update and the opportunity to meet and chat with our Board of Directors. Stories will be told and memorabilia shared to ensure the nurses home receives the farewell it deserves and we look forward to seeing you there!
No need to RVSP- just turn up on the day!
05.08.22
Early works are expected to get underway this month that will be completed by AW Nicholson.
The initial steps will involve demolition and construction of a temporary pathology lab and cafeteria allowing for the main construction works to begin.
The main construction works expected to get underway in early 2023 will replace the old emergency department and add a four-bed short-stay unit as well as mental health patient care and treatment rooms to support people who may need to isolate.
The project is on track to be completed in 2025 and will create nearly 150 jobs during its peak.
The project is being delivered by the Victorian Health Building Authority (VHBA) in partnership with the Federal Government, who are contributing $30 million towards the redevelopment.
https://architectureau.com/articles/designs-released-for-victorian-hospital-revamp/#
08.07.22
SHDH EMERGENCY DEPARTMENT BUILDING RENDER DESIGNS RELEASED
We are extremely excited to share with our community, the much anticipated render designs for the SHDH Emergency Department Redevelopment!
This week, the Minister for Health, The Hon Mary-Anne Thomas released the render designs for the $48.7 million project, which will more than double the number of existing treatment spaces set in a new modern building, an innovative step in the right direction for Swan Hill District Health and the community we serve.
The designs reveal a first look at the new Emergency Department and associated clinical spaces which will create a welcoming atmosphere for patients and their families and will provide a new efficient working space for our staff. These designs have been developed and represented by SHDH Staff User Groups in conjunction with the project Consultant Team.
“We are delighted with the render designs that have been presented. They are the culmination of a lot of dedicated people working together to design the best possible space within the area we have been afforded.” said Chloe Keogh, Acting CEO at Swan Hill District Health, “We are so excited to have reached this stage of the project and look forward to working with our staff and the community on providing a new state of the art Emergency Department for our region and beyond.”
6.05.22
The Emergency Department project has now moved into the Detailed Design phase of the project, which has seen the establishment of key user groups specific to Emergency, Community Health, Occupational Therapy and HARP, Pathology (Austin), Front of House, Security and Café. Key staff representation through all sessions to date has been solid and well represented.
The Detailed Design Phase has an allocation of four (4) workshops for each user group identified. Each workshop is followed up with an Executive group session providing a summary of each workshop and key areas for discussion and decision. Our final Detailed Design Workshop was held last week, following this final week of workshops the consultant team anticipates agreement and sign off of this phase of the project from Swan Hill District Health.
We will then commence with some early works so as to decommission the existing building (old Nurses home) in preparation for the construction phase. Our Early works package includes temporary fit out for Pathology, Café and Community Health staff and their relocation to off site locations for the duration of the project. The project team is currently working on the Construction phasing so as to ensure that while our build is in progress services on site are minimally interrupted.
The new $48.7 Million SHDH Emergency Department development project has officially commenced.
SHDH has held its first meeting for the new Emergency Department development with the Victorian Health Building Authority, the Department of Health and the appointed project consultancy team to officially commence this exciting $48.7 Million project.
The new Emergency Department development will include:
The project consultants appointed to support this development are:
The draft Project Program is summarised as follows:
Our Consultancy Team and the SHDH Project Team will be gaining both staff and community input into the project by way of specific User and Working groups through the design and development phase.
The flow chart below provides an overview of how this project will be managed.
Read about our latest activity, news and upcoming events here in our latest newsletter.
Read more...
Read about our upcoming events, news and services in our latest newsletter edition here.
Read more...
Keep up to date with our latest events, activities and services! Read the Feb edition of Community Health News, here.
Join us in celebrating International Women’s Day on March 8th with morning tea at our new location, 125 Campbell Street, Swan Hill, from 10am until 12noon. Come and see our new site and check out our services and health promotion interventions.
Read more...
Recording from online AGM- Held Wednesday 22nd February 2023:
Read about our services, activities and news from our Community Health team, now based at 125 Campbell Street, Swan Hill, see here: Community Health Newsletter Jan 2023
Read more...
Our old Nurses home is about to be demolished to make room for our new Emergency Department so we held and event on 28th September 2022 to celebrate the history of the building and acknowledge the many and wonderful staff that resided there over 44 years.
Over 100 people attended and shared many interesting stories from their time spent in the building.
Margaret (Meg) Irvine has created information from her stay at the Old Nurses Home from 1979 – 1982 titled “If only these walls could talk!”
Also see ABC Website article.
Swan Hill District Health provides a number of services in the area of cancer care; our care is designed to provide a supportive and welcoming environment for patient and families with a greater focus on overall care including physical, spiritual and emotional wellbeing. We have a team of visiting Medical Oncologists from the Bendigo Cancer Centre that come to Swan Hill once a month to provide face to face services for their clients without the concern of having to travel. Whilst your care may not be under the Bendigo Cancer Centre we also have a number of other services to assist cancer patients and there families in the Swan Hill region.
Chemotherapy
Staffed by specialist chemotherapy nurses, under the guidance of Bendigo Cancer Centre oncologist’s. Available from Tuesday—Friday.
Telehealth Oncology
Along side the monthly oncology visit we also provide monthly telehealth session between client/family oncologist and chemotherapy nurses.
McGrath Breast Care Nursing Services
Service managed by a specialist breast care nurse. Provides supportive care for clients and families following a diagnosis of breast cancer. Available Monday to Thursday with alternate Tuesdays.
Cancer Care Coordinator
Provides supportive care for people diagnosed with cancer and their families. There as a support, advocate and contact for patients and families, when diagnosed with cancer. Available Tuesday – Thursday.
Lymphoedema Services
Run by a lymphodema trained physiotherapist where patients are provided with education and management advice for those people with or at risk of lymphedema.
Oncology Exercise Group
Offered to patients undergoing cancer treatment or within 12 months of completing. Appropriate exercise has shown to help manage some common side effects of fatigue, loss of muscle mass, speed up recovery and to improve your quality of life. Available Monday and Wednesday.
Wig Service
Swan Hill District Health is the lead agency for the coordination of the vital local Wig Service. A local hairdresser will work with you to help choose, order and fit your wig.
Allied Health
We have a number of allied health services that can also assist you throughout your treatment including physiotherapy, exercise physiologists, occupational therapists, podiatrists, dietitians, speech pathologists, social work and counselling.
Advance Care Planning
Enable you to share with your family, doctor and those close to you, your preferences, beliefs and values in regards to your future healthcare. Available Fridays
Palliative Care
Is specialised care and support provided in the community for someone living with a life threatening or life limiting illness. It is designed to improve quality of life for clients, their families and caregivers.
We offer services for prevention via community education and clinical services for National screening programs such as the Cervical Screening Test.
Cancer patients can receive support and treatment from our medical and multi-disciplinary team to ensure optimal care within the Swan Hill region.
For enquiries on any of these services, please contact:
Cancer Care Coordinator
Tuesday – Thursday
125 Campbell Street, Swan Hill
Phone: (03) 5033 9201
Or go to our Cancer Services page
Read more...